03 Jun New Dosing Hut and Generator Installation, Orange Walk
Project Name: Orange Walk New Dosing Hut and Generator Installation
Location: Clarke Street Pump Station Compound, Orange Walk
Project Manager: Mr. Richard Bowman
Project Engineer Supervising Works: Mr. Ryne Timmons and Mr. Richard Bowman
Project Cost: $125, 000.00
Duration of the Project: 6 months
Contractor: De’Mar’s Stone Company

Project Objectives:
Provide standby generator to supply water to the community more efficiently during a BEL power outage, especially one caused by a tropical cyclone.
Project Status:
The construction of 135 square feet concrete addition to Clarke Street Pump Station and purchasing and installation of new generator is approximately 80% completed. The contractor has completed plastering and is currently working on refurbishing and installation of doors.