Rebuild Suspension Bridge to Cross River, Benque

Rebuild Suspension Bridge to Cross River, Benque

Upcoming Project: Rebuild Suspension Bridge to Cross River, Benque

Estimated Cost: $190,000.00

Contract Given: Mr. Ramon Martinez

Project Manager: Mr. Sanjay Keshwani

Project Engineer: Mr. Edward Eck

Tested and available flow rate from the spring: 185 GPM1

Duration of the construction: 6 months

Reason Required

During 2008 heavy floods due to Tropical Depression 16 destroyed the suspension bridge located on the Benque River. The bridge used to support a 6 inch PVC pipe to supply water to the Benque community from a spring located on the other side of the river.</p> <p>Presently, Benque community is fed by two ground water wells. The dynamic levels of these wells keep falling. Therefore, the pumps need to be lowered almost every dry season. Rebuilding the existing suspension bridge will allow us to connect back the spring with our system providing extra capacity for the water supply system.

General Scope of Works:

  • Remove existing steel columns
  • Supply all material required to build new bases for new steel columns
  • Build new bases for steel columns
  • Supply and install new steel columns as per drawings and specification
  • Break existing stair case on pump house side
  • Excavate ground to required depth to receive concrete caps
  • Supply and install concrete caps on existing anchors on both side
  • Pull main 1.25 inch diameter cable 1 foot from each side to decrease sag by 2 feet at middle.
  • Install 6 inch ductile iron pipes across the river as per drawings and specifications
  • Remove rust of all steel members
  • Apply grease to all joints and fasteners of steel members
  • Prime and epoxy paint all steel members
  • Build Chlorinator house as per drawing and specification
  • Clean site and dispose of all material as per Belize’s environmental rules and regulations